CHAPTER 8

 

SUMMARY

 

8.1 The foregoing text was prepared with only one purpose: to provide guidance to individuals and organizations in the process of contracting for consultant/construc­tion services. The possible variation in type, size, complexity, location and method of project realization is far too great to permit a volume of this size to deal with more than generalities for most of the subjects covered. Specifics have been provided only for subjects which are usually not affected by the variations mentioned above.  Even these should be examined carefully to be certain they are applicable.

 

8.2  The most significant steps for any project are;

(a) Task identification - the sponsor must identify what must be accomplished, the time frame for its completion, and the budget available for the work.

(b) Assembly of background material - the sponsor should research thoroughly all available data; physical, technical, statistical and socio-economic which will affect the magnitude and/or conduct of the work effort.

(c) Preparation of invitations for proposals - the degree of detail included in the invitations regarding the terms of reference, scope of work and contract conditions should be commensurate with the size and complexity of the project.

(d) Selection of consultant - this should be made on the basis of recent past accomplishments and reputation with comparartive, competitive fees being a lesser consideration.

(e) Consultant contract type - unless law or other rules dictate otherwise, the type of contract (.fee basis) should be a negotiable item and the type chosen should take into account the probability of future modifications to the scope of work and the easiest possible way to do this while minimizing the administrative burdens on both parties.

(f) Selection of contractor - this should be made on the basis of competitive bids after an examination of the bids for correctness, completeness and proper balance of individual unit prices. The contract type should be established by the sponsor taking into account the probability of future modifications to the scope of work.

g) Negotiations - these should be conducted in a. co-operative atmosphere with the willingness of each party to try to understand and accommodate the requirements of the other. The negotiation process will have a lasting effect on the conduct of the project.

h) Contract administration - all the functions listed in the text must be carried out thoroughly and expeditiously; none more so than the prompt processing of invoices.