Guidance On The Development Of An SMS Implementation Plan
For Service Providers
( All
Certificate Holders )
Background
As part of ECAA safety programme; ECAA
mandates that an [operator, maintenance organization, ATS provider, certified
aerodrome] implements a safety management system (SMS) accepted by the ECAA that,
as a minimum: .
1- Identifies safety hazards.
2-Ensures that remedial
action necessary to maintain an acceptable level of safety is implemented.
3-Provides for continuous
monitoring and regular assessment of the safety level achieved.
4-Aims to make continuous improvement to the
overall level of safety. "1"
The following guidance should be used as
reference to develop an SMS implementation plan that explains how a service provider
organization will implement an SMS on the basis of ECAA requirements and
international Standards and Recommended Practices (SARPs), the system
description and the results of a gap analysis.
It is important to understand that the
suggested plan is intended to be used only as reference guidance and it
may need to be tailored to meet the needs of each service provider
The development of an appropriate and
realistic SMS implementation plan will :
1- Assist service providers in preparing a
realistic strategy for the implementation of an SMS that will meet the
organization’s safety needs
2- Define the approach the organization will
adopt for managing safety
3- Provide sequential steps on how to
implement SMS
4- Provide an accountability framework for
the implementation of the SMS
Two requirements should be completed prior to
developing the SMS implementation plan , identify the accountable executive and,
the safety accountabilities of managers.
Accountable executive must have:
1- Full authority for human resources
issues.
2-Authority for major financial issues.
3- Direct responsibility for the conduct of
the organization’s affairs.
4- Final authority over operations under
certificate.
5- Final responsibility for all safety
issues.
6-Identify the person (or
planning group) within the organization responsible for developing the SMS
implementation plan .
The
success of the proposed SMS implementation plan depends on the support,
commitment and participation of management, supervisors and line
operational personals. A Phase approach is suggested for the development of the
SMS implementation plan and the timeline for its implementation may be
different, depending on the complexity of the organization.
SMS
Implementation Plan – building blocks
(1)Safety
planning and objectives
(2)Safety
policy
(3)Safety
roles and responsibilities
(4)System
description
(5)Gap
analysis
(6)Hazard
identification processes
(7)Risk
management processes
(8)Safety
performance measurement
(9)Safety
training
(10)Safety
communication
(11)Coordination
with third parties
(12)Management
review (of safety performance)
SMS
Implementation Plan – Phase approach
Phase 1- Safety Policy and Objectives (Planning)
This phase should be the blueprint on how the SMS
requirements will be met and integrated to the organization’s work activities.
In order to achieve that, the following issues should be completed,
(a) Management commitment to SMS implementation:
(1) Identify the safety
objectives of the organization
(i) Objectives
as a precise tangible elements to be validated (through the different phases)
and linked to the safety performance indicators and safety performance targets.
(2) Develop a safety policy
that contains at least addressed the following points :-
(i) Achieve the highest
safety standards.
(ii) Observe
all applicable legal requirements and international standards, and best
effective practices.
(iii)
Provide appropriate human and
financial resources.
(iv)
Enforce safety as one primary
responsibility of all managers.
(v)
Ensure that the policy is
understood, implemented and maintained at all levels.
(3) Establish allocation of
time for the SMS processes among the different management layers of the
organization
(b) Management must establish the level of expectation
for the SMS and its usage by contractors and sub-contractors on their jobsites
(1) Write SMS requirements
into the contracting process
(2) Establish the SMS
requirements in the bidding documentation
(c) Safety communication
(1) Communicate, with
visible endorsement, the safety policy to all staff
(2) Establish means to
communicate safety related issues that could include:
(i) Safety policies and
procedures
(ii) Newsletters
(iii) Bulletins
(iv) Website
Elaboration of System Description and Gap Analysis
(a) Establish the guidelines for system description
and the interaction of its different components
(1)Required human performance considerations of the system
operation
(2)Hardware components of the system
(3)Software components of the system
(4)Operational environment
(5)The system interactions with other systems in the air
transportation system
(6)Contracted and purchased products and services
(b) Perform Gap Analysis
against the four components and thirteen elements of the SMS framework as
specified below .
(1) Safety policy and objectives
(i)
Management commitment and responsibility
(ii)
Safety accountabilities of managers
(iii)
Appointment of key safety personnel
(iv)
SMS implementation plan
(v)
Coordination of emergency response planning
(vi)
Documentation
(2)
Safety risk management
(i)
Hazard identification process
(ii)
Risk assessment and mitigation process
(3) Safety assurance
(i)
Safety performance monitoring and measurement
(ii)
The management of change
(iii)
Continuous improvement of the SMS
(4) Safety promotion
(i)
Training and education
(ii)
Safety communication
(c) Identify
potential challenges in the implementation, develop plans to
address challenges (i.e. risk assessment of the plan)
With the results of the gap analysis the implementation team
should develop an SMS structure and determine the safety responsibilities of
key personnel
Establishment of SMS Organizational Structure
(a) The implementation planning team to propose an SMS
structure; and,
(b) Safety responsibilities of key personnel :-
(1) The safety office –
Corporate functions
(i)Advising senior management on
safety matters
(ii)Assisting line managers
(iii)Overseeing hazard
identification systems
(2) The safety manager –
Responsibilities
(i)Responsible individual and focal point for the development and
maintenance of an effective safety management system
(ii)The safety manager functions and selection criteria
(3) The Safety Review Board
(SRB):
(i)High level committee
(ii)Strategic safety functions
(4) Safety Action Group(s)
(SAG):
(i)Reports to SRB and takes strategic direction from SRB
(c)Approval of SMS implementation plan and initial training
(1)Draft SMS implementation plan developed
(2)Identify the costs associated to training and planning of the
implementation
(3)Draft budget for SMS implementation
(4)Approve initial budget for SMS implementation plan
(5)SMS implementation plan signed by accountable executive
(d) Training
(1) Introduction of SMS
concepts accordingly to the level of all staff, contractors and sub-contractors
(2) Identify who needs to be
training for further phases
(3) Identify the costs
associated to training
(4) Organize and set up
schedules for training of all supervisors and staff
Coordination of the emergency response plan
(a) Internal coordination
(1) Emergency planning team
established.
(2) Emergency planning
coordinator appointed .
(3) Procedures in place .
(4) Others
(b) External coordination
(1) Established with search
and rescue services
(2) Established with Egyptian
Civil Aviation Authority (ECAA) and investigation agencies
(3) Emergency Action Plan
submitted to ECAA
(4) Others
Documentation
(a) Develop the safety
library of the organization
(b) Development of SMSM
(related to planning phase)
(c) Safety library in
place
(d) Information on Phase 1
collected and distributed to the organization
Phase 1 Timeline - 1 to 6 months
Depends on the complexity of the organization
Deliverables:
(a) Safety objectives of
the organization approved by accountable executive
(b) Safety Policy signed by
accountable executive
(c) Safety Policy
distributed all across the organization
(d) SMS organizational
structure in place
(e) Lines of safety
accountability established
(f) Approval of SMS
implementation plan and initial training
(g) Emergency response
planning in place
Milestones:
(a) Draft proposal of
safety policy
(b) Gap Analysis results
delivered
(c) Proposal of SMS
organizational structure including allocation of resources and time for the SMS
processes among the different management layers of the organization
(d) Estimated budget for
SMS processes
Phase 2: Safety Risk Management (reactive processes)
Means
of collecting, recording, acting on and generating feedback about hazards and
risks in operations according to the results of the gap analysis
(a) Determine what form of
intervention tool to be used to collect reactive information
(b) Decide which reporting
system will be required and adapted to the organization.
(1) Mandatory reporting
system
(2) Voluntary reporting
systems
(3) Confidential reporting
systems
(c) Determine what Matrix
to be used or a new creation.
(1) Customize the Risk
Matrix to suit the organizational complexity
(2) Develop Risk Matrix
instructions on the forms and/or in the training
(d) Determine
risk management levels to be documented (i.e. intolerable, tolerable or
acceptable)
(e) Write such
requirements into the bid documentation for contractors, if necessary and
notify contractors and sub-contractors in writing.
(f) Identify administration
process/responsibilities for
implementing strategies
(1) Will we need a database
to capture reactive data from forms?
(2) Who will maintain
filing/database?
(3) Who will analyze data
for trends?
(4) How will trends be
communicated to?
(5) Develop control and
mitigation strategies (for reactive processes)
(g) Build the safety
library
(h) Collect information for
safety performance indicators
(i) Train-the-Trainer(s)
(j) Train the
Managers
(k) Train the front line personnel
(l) Provide
ongoing coaching and guidance by supervisors or ( Managers) to front line
personnel
Phase 2 Time line - 6 to 18 months
Depends on the complexity of the organization
Deliverables :
(a) Safety reporting system
(for reactive processes) in place
(b) Safety library in place
Milestones :
(a) Risk assessment matrix
in place for reactive processes
(b) Formal procedure to
translate operational safety data into hazard-related information
(c) Training on reactive
processes completed for operational personnel , managers and supervisors
(d) Convey safety critical
information to the organization based on reactive processes
Phase 3: Safety Risk Management (proactive and predictive
processes)
(a) Determine what form of
intervention tool to be used to collect proactive and predictive information
(e.g., confidential reporting systems, flight data analysis, normal operations
monitoring etc.)
(b) Update guidelines,
procedures, hardware and software to support the proactive and predictive
intervention tools.
(c) Review and update the reporting policy
(d) Identify administration
process/responsibilities
(1) Will we need a database
to capture proactive and predictive data from forms?
(2) Who will maintain
filing/database?
(3) Who will analyze data
for trends?
(4) How will trends be
communicated to?
(e) Train flight safety
manager on specific intervention tools on collecting information
(f) Determine risk
management levels to be documented (as
in phase 2)
(g) Use the risk matrix as
in Phase 2
(h) Develop control and
mitigation strategies
(i) Brief supervisors and
frontline personnel on proactive and predictive processes
(j) Requirements into the
bid documentation for contractors and sub-contractors in writing
(k) Develop safety
performance indicators and targets
Phase 3 Time line - 6 to 12 months
Depends on the complexity of the organization
Deliverables –
(a) Safety reporting system
(for proactive and predictive processes) in place
(b) Safety performance
indicators and targets approved by CEO
Milestones –
(a) Risk control/mitigation
strategies developed
(b) Safety performance
indicators and targets reviewed by the Safety Review Board (SRB) or equivalent
(c) Training on proactive
and predictive processes completed for operational personnel, managers and
supervisors
(d) Convey safety critical
information to the organization based on reactive processes
Phase 4: Operational Safety Assurance and Safety Promotion
Acceptable levels of safety
(a) Define safety
performance indicators and safety performance targets of an acceptable level(s)
of safety of the organization
(b) Establish safety
requirements to deliver the safety performance indicators and safety
performance targets of an acceptable level of safety
(c) Acceptable levels of
safety established and submitted to the ECAA
Safety performance monitoring and measurement .
Define the process by which the safety performance of the
organization is verified in comparison to the approved safety policies and
objectives
(a) Safety reporting
(b) Safety studies
(c) Safety reviews
(d) Audits
(e) Surveys
(f) Internal safety
investigations for occurrences or events that are not required to be
investigated or reported to the ECAA
(g) Define safety
performance indicators and safety performance targets of an acceptable level(s)
of safety of the organization
(h) Establish safety
requirements to deliver the safety performance indicators and safety
performance targets of an acceptable level of safety
(i) Establish lines of
accountability for measures of reliability, availability and/or accuracy
related to safety requirements
Management of change
Assess internal and external changes
(a) Identify affected
established processes and services
(b) Arrangements to ensure
safety performance
SMS continuous improvement:
(a) Proactive evaluation of
facilities, equipment, documentation and procedures completed through audits
and surveys
(b) Proactive evaluation of
the individuals’ performance completed to verify the fulfilment of their safety
responsibilities
(c) Procedures for Reactive
evaluations in place to verify the effectiveness of the system for control and
mitigation of risks ( accidents, incidents and major events investigations)
(d) Training relevant to
operational safety assurance
(e) Documentation relevant
to operational safety assurance
(f) Identify changes
required from trend analysis of Risks being reported
Safe
Work Practices being updated
Additions
to the Safety Program
Safety Promotion
Effective methods to promote safety in this phase should include
among others:
(a) Review, revise and
communicate changes to your organization’s SMS usage and standards
(b) Share “lessons learned”
that promote improvement of the SMS
(c) Identify methods to
communicate successes of SMS (i.e. after training is completed, trends
identified in the documentation submitted, changes to the safety related
programs, etc.)
(d) Review safety policy
including the reporting policy
(e) Promote participation
by all personnel in the identification of hazards
Phase 4 Time line - 4 to 12 months
Depends of the complexity of the organization
Deliverables:
(a) Acceptable levels of Safety established and submitted to the
Egyptian Civil Aviation Authority
(b) Revised Safety
strategies and processes approved by the CEO
Milestones:
(a) Processes for safety
performance monitoring and measurement approved and established
(b) Re-evaluate strategies
and processes by the SRB
(c) Training on proactive
and safety assurance completed for operational personnel, managers and
supervisors.